Non-Compliance detail


  
Summary
 
Licence number: 2122
Annual Return Start: 27 Jul 2006
Annual Return End: 26 Jul 2007
Date Received: 26 Sep 2007
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M3.1 The sampling plane locations in the boiler ductwork do not satisfy AS4323.1 - 1995 with regard to up/down stream distances from disturbances. Flow conditions at the sampling plane are turbulent. Liddell will be installing new sampling point by Dec07. Appropriate Action taken by licensee 1